April 2018 OC Fairgrounds Master Site Plan Concept and Proposed Phasing Released

The OC Fairgrounds (Orange County Fair and Event Center aka OCFEC) has released the draft of the process for the Master Site Plan and draft proposal with phasing of costs. Problematic elements featured in the prior Master Site Plan proposal such as demolition of the recently constructed Main Mall and construction of massive convention center buildings have been removed from the proposal. The proposed phasing of the construction is:

Phase I - Expand Administration Building at a cost of $22.9 million.
Phase II - Replace livestock barn, upgrade Action Sports Arena & equestrian facilities relocation and upgrade at a cost of $21.8 million.
Phase III - Repurpose current equestrian center space at a cost of $16.1 million.
Phase IV - Build new education center and upgrade Centennial Farm at a cost of $27.4 million.
Phase V - Install perimeter fence at a cost of $9.4 million. 
Phase VI- Relocate Main Entrance to align with Main Mall at a cost of $50.8 million. 
Phase VII - Build parking garage and bridge to OCC at corner of Fairview Road and Arlington Drive. 
 
A draft proposal is posted to be considered at the April 2018 Board meeting and is available for download here.  Download CHJC-OCFEC-Board-Presentation-April-2018-FINAL-DRAFT_040218
 
The constraints placed on the proposal included:
  •  No negative impact on the annual fair

  • Engage the OC Marketplace ownership on proposed changes

  • Review parking and engage Orange Coast College in parking opportunities

  • Insure education facility needs are reviewed

  • Re-visit community opportunities

  • Review Equestrian Center and Equine opportunities

The Master Site Plan Process Milestones to date are:

  1. Early to mid-2016 developed a Request for Proposal (RFP) to find a Master Site Planning (MSP) consultant

  2. Awarded a consulting contract to Johnson Consulting November 2016

  3. First quarter of 2017 information gathering

  4. January 2017 OCFEC Board of Directors stakeholder meeting

  5. March 2017 OCFEC staff stakeholder meeting

  6. April 2017 on grounds partners stakeholder meeting

  7. May 2017 facility users stakeholder meeting

  8. June 2017 Community partners stakeholder meeting

  9. June 2017 Town Hall public meeting

  10. September Board of Directors workshop

  11. Late 2017 early 2018 Develop CEQA consultant RFP

The next steps are:

  1. April 2018 Board of Directors workshop – work towards finalizing draft MSP concept

  2. Date, TBD, (Evening, May 2018) hold public meeting to present the draft MSP concept

  3. April 2018 award CEQA consultant contract

  4. Over the next several months work through the CEQA process